Commission narrowly approves first reading of one‑year pause on some high‑density multifamily applications
Summary
On first reading the board enacted a one‑year pause on new RM‑8 and RM‑16 zoning applications (high‑density multifamily) after lengthy debate over sewer capacity, traffic and pipeline of approved units; the measure passed 3–1 on first reading after narrowing scope.
Get email alerts on the Housing Policy topic
No spam. Unsubscribe anytime.
Mount Juliet — The Board of Commissioners voted on first reading to impose a one‑year pause on the acceptance of new RM‑8 and RM‑16 zoning applications, a measure its sponsor described as a temporary, targeted pause to allow review of infrastructure and planning implications.
Commissioner Heffner, sponsor of the ordinance, said the intent was limited and temporary: “This is a 1 year pause on the acceptance of applications for high density housing,” he told the board, arguing that apartment projects can deliver hundreds of units at once and therefore can produce a concentrated near‑term impact on roads, schools and utilities.
Board debate was extensive. Supporters cited the city’s inventory of units already approved or under construction (the transcript records commissioners noting roughly 4,422 residential units under construction and about 2,007 already approved) and vulnerabilities in sewer capacity in parts of the city. Public‑works staff explained capacity has been allocated for approved projects and a trunk‑line upsize is in the capital plan; staff also said projects already in the pipeline would remain unaffected by the pause.
Opponents warned of unintended consequences. Commissioner Malelli argued that a broad pause could increase sprawl and reduce housing supply; she urged targeted measures that restrict only developments that fail infrastructure capacity tests or that require additional fiscal guarantees. Others warned that stripping CMU/CTC from the text (an amendment the board adopted) would reduce the ordinance’s effectiveness because many higher‑density projects arrive under CMU zoning. The sponsor agreed to narrow the text to RM‑8 and RM‑16 and struck references to CMU and CTC before the vote.
The measure passed first reading 3–1; the board also discussed MTAS guidance recommending against moratoria longer than 12 months and staff said the ordinance could be revisited after the year if necessary.
What’s next: The ordinance will return for second reading if the board votes to advance it; projects already in the approval pipeline will proceed under existing entitlements, staff said.