Doorwater staff outline bridge and road schedules, utility relocations
Summary
Staff reported utility coordination for the Bad Pack Road Bridge with pole relocations and a May 29 schedule target, pre-construction activity and a Whispering Sands MOU for Rudy Road, and contract-completion and start dates for Bridge 132 (Aug. 7) and Mineral Springs Road (Feb. 2).
At the Jan. 27, 2026 Doorwater Management Commission meeting, staff gave updates on several bridge and roadway projects, noting utility coordination, right-of-entry work and target construction dates.
Speaker 3 said the Bad Pack Road Bridge team held a utility coordination meeting and confirmed that utility plan review timelines (about 75–90 days) are in process. "We are gonna get right of entry on the left side of the bridge where…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat