Morgan City Council approves 2026 street-maintenance contract with Post Asphalt

Morgan City Council · January 28, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Morgan City Council unanimously approved Resolution 26-03 authorizing an agreement with Post Asphalt & Construction for the 2026 street maintenance project, approving unit pricing and allowing change orders to extend work where savings permit.

Morgan City Council voted unanimously Jan. 27 to authorize an agreement with Post Asphalt & Construction for the city’s 2026 street maintenance work, including a 26th Street maintenance scope and authority for staff to negotiate change orders as needed.

Staff presented a plan that pairs a thin “level course” (about 1–1.5 inches in the center) with a chip seal finish for parts of the Red Rock subdivision. Lance, a city maintenance staffer who presented the plan, said that approach smooths rutted trenches and preserves pavement while saving “about $100,000” compared with a full overlay for the same sections. He told the council that comparable methods have worked in other municipalities and that good unit pricing made it feasible to consider additional city-wide work under the same contract.

The measure (Resolution 26-03) explicitly authorizes the mayor and staff to finalize the contract with Post Asphalt & Construction and to approve negotiated change orders within the approved process. A council member moved approval after brief technical clarifications; the motion was seconded and the mayor called a roll call. The resolution passed unanimously.

Council members and staff discussed timing and budget impacts: crews and contractors are being scheduled to bid early in the year to capture lower rates, and the city expects work to begin when temperatures permit (staff estimated field work starting in late spring, with chip sealing and fog sealing completed in phased steps). Staff noted the project will require a budget amendment because some work scheduled from the previous year rolled into the current budget cycle; the council said it planned to approve an amended budget later in the fiscal year to accommodate the accelerated schedule.

What happens next: staff will finalize unit pricing, execute the contract with Post Asphalt & Construction, and coordinate field scheduling and any necessary change orders under the resolution’s authorization.