County staff to negotiate with recommended contractor on five-unit affordable housing project

San Miguel County Board of County Commissioners · February 4, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

San Miguel County staff recommended Prosette Construction for negotiations on a two-phase construction manager/general contractor approach for a five-unit affordable housing project; preliminary cost estimates put per-unit prices near $500,000 and total project costs around $2–2.5 million.

County housing staff told the board they received four competitive proposals for the on-call affordable housing project at 686 County Road 63L and recommended negotiating with a local firm, Prosette Construction, for preconstruction and construction services.

Housing specialist Drea Bridal summarized project status: schematic design and geotechnical work are complete, the project is at roughly 30% design, and the RFP process (published Dec. 10; proposals due Jan. 23; interviews Jan. 30) produced two leading candidates. "We plan to hire a construction manager or general contractor for the 2 phases," Bridal said, describing Phase 1 (preconstruction: cost estimating, value engineering) and Phase 2 (construction under a guaranteed maximum price to be presented to the board for later approval).

Staff presented preliminary cost ranges: preconstruction $32,000–$46,000; construction estimates in the $1.9M–$2.0M range; total project cost estimates roughly $2.0M–$2.5M. Bridal said average cost per unit for top firms was about $499,000–$508,000. Jared Biggs, deputy county manager, noted Prosette’s local knowledge and site-specific strategies as reasons for recommending them to lead negotiations.

Commissioners asked about value-engineering steps to reduce per-unit cost; staff said the contractor will propose alternatives (retaining-wall strategies, electrical routing, modular options) and that a finalized, 100% construction package and contract will be presented to the board before construction approval.

Board action: commissioners expressed broad support for staff to proceed with negotiations and requested staff return with the negotiated contract and any recommended GMP for formal consent on a future agenda.