Commission grants partial pavement variance and defers local-road requirement for Naumann addition plat

San Angelo Planning Commission · September 16, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The commission approved FP2522 (Naumann Addition Section 2, Lot 1) with a partial variance to widen East 28th Street to 26 feet with curb and gutter and deferred construction of a planned local road via a developer agreement; vote was unanimous (6–0).

The San Angelo Planning Commission approved a final plat for the Naumann Addition (FP2522) and granted a partial variance on road width while deferring construction of a new local road to a developer agreement.

Austin Reed, senior planner, described the application as a final plat creating a single 11.98-acre lot in a light-manufacturing (ML) zone. The applicant requested two variances: to keep East 28th Street at 18 feet (the existing width) rather than bringing it to the standard width, and not to construct a new local road shown on the plat. Staff recommended a partial variance — bringing East 28th to a minimum of 26 feet with curb and gutter — and allowing a deferral for the new local road through a developer agreement.

City engineering weighed in on street construction standards. Kevin Bates, city engineer, recommended a ribbon curb rather than a caliche base for temporary turnarounds and explained that the subdivision ordinance accommodates phased development through deferral agreements that can mitigate upfront paving costs.

Commission discussion focused on safety and long-term maintenance: commissioners asked about curb types, minimum widths required by the city’s Land Development and Subdivision Ordinance (LDSO), and how a deferral would be memorialized. Staff confirmed deferrals are recorded with the plat and typically include triggers or time limits; they noted a deferral can be tied to future development events or a specified time period.

On a motion from a commissioner and with a second, the commission approved the plat with the partial variance for paving and curb and gutter on East 28th Street and approved deferral of the local-road construction (to be managed through a developer agreement or financial guarantee). The motion passed unanimously, 6–0.

Next steps: staff will work with the applicant on the partial-variance conditions, right-of-way dedication and the developer-agreement terms that memorialize the deferral.