Norwood building committee approves invoices, several change orders and rejects gym‑floor claim

Bridal School Building Committee · February 10, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

At a Feb. 9 meeting, the Bridal School Building Committee approved December and January invoice packages, authorized change orders to finish turf drainage and field wall pads, accepted a Sintra panel credit and denied an $88,005.31 contractor claim for gym‑floor repairs; staff detailed multiple punch‑list items to be finished this spring.

BRIDAL SCHOOL BUILDING COMMITTEE — NORWOOD — Feb. 9, 2026 — The Bridal School Building Committee heard a broad project update and approved a series of invoices and change orders while rejecting a contractor claim related to gym‑floor repairs.

Speaker 6, presenting the project update, told the committee the rebuild is tracking favorably against the 2022 town meeting objectives: estimated project costs were originally put at $150 million and the team now projects a final cost just over $140 million. The Massachusetts School Building Authority (MSBA) facility grant was discussed — originally cited at roughly $46 million and later raised in a 2024 amendment to about $52 million — and the project team said final MSBA reimbursement will depend on the MSBA's final audit. Speaker 6 said the team is targeting the 10‑month commissioning walkthrough in June and a gym‑floor rescreen and recoating in August to complete punch‑list work prior to the next school year.

While the budget outlook was described as “overall positive,” staff reviewed a long list of warranty and punch‑list items that remain open. Speaker 6 reported three minor roof leaks detected in December and January (locations: fourth‑floor outside a classroom near room 453, the gym entry, and a stairwell). The team intends to reinspect and recertify the roof after spring thaw; Speaker 9 committed to provide…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans