District consultant reports Phase 1 punch-list near completion; Phase 2/3 schedules laid out
Summary
A Palumbo Group / Clark Patterson Lee representative told the board that Phase 1 of the 2022 capital bond is substantively complete, punch-list work remains, and Phase 2 (including high-school rooms) and Phase 3 (HVAC and field work) have target summer start and completion windows.
A representative for Palumbo Group and Clark Patterson Lee updated the South Orangetown Central School District Board of Education on progress under the district's 2022 capital bond, describing Phase 1 substantially complete and detailing timelines for remaining work.
The presenter said Phase 1 substantial completion was recorded on Aug. 23 and that district staff and contractors are closing out punch-list items. Phase 1 work covered four…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat