County staff give updates on bridge, signal and local maintenance projects
Summary
Staff briefed commissioners on bridge replacement schedules, environmental constraints delaying combined bids, the 65th South bridge wall work, and a local asphalt repair request at a park entrance.
Get email alerts on the Infrastructure Updates topic
No spam. Unsubscribe anytime.
County staff provided a series of public-works updates covering bridge projects, signal installations and small-scale maintenance requests.
Unidentified Speaker 2 summarized signal work, saying the right-of-way activity had to be finished before producing the final PS&E and engineer's estimate and taking the project to bid: “We needed to finish the right away activity, and then we could get the final PS and E … We then we need to go out to bid for it and, just all start the constructive process.” Staff estimated roughly 1.5–2 months to reach the bid process and “the project itself construction time is only anticipated to be between 60 and 90 days.”
On bridges, staff described efforts to combine two bridge projects north of 29th and 26th pending resolution of environmental issues at Willow Creek. Progress was reported on the 65th South bridge replacement: “They are due to 4 of the walls on the 65th South Bridge replacement project tomorrow… they are making good progress on that bridge. The walls are very substantial.” Staff said the design was modified before bid to accommodate a future five-lane arterial, making the new bridge wider than the old structure.
A local maintenance request was raised by Unidentified Speaker 1 seeking a small asphalt fill around an asphalt ramp in a park entrance; Unidentified Speaker 2 agreed to inspect and coordinate the patch crew. The meeting also included coordination about accommodating trucks and equipment related to a shooting-range facility and working with the fire department for safety and staging.
No substantive policy decisions were made in these updates; staff provided status, timing estimates and next steps for construction and maintenance planning.