Houston County approves $1.679 million GMP for HEMA storage warehouse
Summary
The Houston County Board of Commissioners approved a guaranteed maximum price of $1,679,073 with Parish Construction Group Inc. for a HEMA storage warehouse, funded from reserve funds and included in the FY25 budget; commissioners said the facility will increase efficiency for emergency management and the sheriff's office.
Get email alerts on the Hema Warehouse topic
No spam. Unsubscribe anytime.
The Houston County Board of Commissioners on Jan. 6 approved a guaranteed maximum price (GMP) of $1,679,073 with Parish Construction Group Inc. for a HEMA (Homeland Emergency Management Agency) storage warehouse. Commissioner Gottwald moved to approve the GMP, the motion was seconded by Commissioner Byrd and carried unanimously.
County officials said the project was included in the fiscal year 2025 budget and will be funded from reserve funds. Commissioners discussed a revised target delivery date of July 1, 2026. Chairman Purdue called the GMP approval an important milestone and thanked Public Works and the construction team for reaching the contract stage.
Chief Stoner, who spoke during public comment as the county’s fire/chief official, praised the selection and the price, saying the proposal kept the county "well under what we had hoped for" and that the new facility will "greatly benefit the citizens" by improving efficiency for emergency response and the sheriff’s department.
County leaders noted the project will colocate emergency management storage and provide a purpose-built facility adjacent to existing county operations, which they said will speed response times during disasters and streamline resource distribution. No changes to the GMP were proposed at the meeting.
The board took the vote as part of its consent agenda and did not set new milestones beyond the projected July 1 delivery date. The county did not provide a construction schedule or detailed budget line items during the meeting; those details were reported as included in the FY25 budget but were not specified in the public record presented at the meeting.