Commission pauses Kimley-Horn design work on North Washington Street amid cost concerns
Summary
A feasibility review for the North Washington Street extension produced a cost'benefit ratio below 1; commissioners directed staff to issue a stop-work letter to the consultant (Kimley-Horn) and to return with revised scope and legal guidance on reallocating bond funds.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
Commissioners on Dec. 16 questioned whether continuing to spend the $1,055,000 design contract with Kimley-Horn was prudent after staff'commissioned analyses showed a cost'benefit ratio below 1 for the initially conceived project.
Staff said an alternative alignment (alternative 4) reduces estimated construction to about $3.5 million, but that even with the alternate design the cost'benefit ratio remained below 1. Commissioners pressed for a legal opinion on whether bond funds allocated for the project could be reallocated if the design did not advance to construction.
After discussion, staff agreed to issue a written stop'work notice to the consultant, cease further billable activity, and return with a revised scope and updated pricing for the alternate option, plus legal guidance on reallocating bond proceeds. Several commissioners expressed concern about paying a high design fee for a project that may not be built; staff said Kimley-Horn is amenable to scope adjustments.