KRTA reviews 10-year bridge plan and funding paths, flags possible millage

Kiwanis Regional Trail Authority (KRTA) · February 11, 2026

Loading...

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Kiwanis Regional Trail Authority reviewed a detailed 10-year bridge maintenance plan calling for roughly $224,000 in year‑one work and an annual target near $250,000; members discussed grant matches, fundraising and whether a millage or intermunicipal commitments are needed for long‑term stability.

The Kiwanis Regional Trail Authority on Monday heard a detailed 10‑year plan for bridge maintenance and prioritized three years of work it called the highest priority.

The plan presenter said the first‑year package is priced at $224,000, which includes a design fee (about 10 percent) and construction engineering inspection and oversight. He told the board the program was modeled on an earlier structure report and assumes a 5 percent annual escalation in construction costs.

Board members pressed on how the plan was built and how it would be paid for. One member cited the $1.18 million figure used previously for a multiyear package but noted that estimate did not include design and oversight costs; with those added, total program costs rise. Another member proposed bundling the first three years and seeking roughly $650,000 in grants or fundraising to cover immediate priorities.

Speakers emphasized the limited internal capacity to commit large matches. "With any of these grants, they're going to ask for a match of some percentage," one board member said, adding typical matches run "20 to 50 percent." The presenter said the authority had targeted roughly $250,000 per year as a sustainable threshold.

Board members discussed a millage as a longer‑term solution to bundle work and enable bonding: "With the millage, even if it's a quarter or a half, you can bond, and we can take care of these bridges all at once," a member said. Others cautioned that a millage would require careful messaging and buy‑in from the four municipalities that share the trail.

The authority took no binding financing decision at the meeting; members asked staff and trustees to pursue follow‑up conversations with township supervisors and potential grant sources and to return with options.

The presentation and subsequent budgeting questions took place amid a broader history of past fundraising and a DNR grant that required a local match. The board noted prior campaigns, COVID‑era cost escalation and the county's former role as the grant applicant when earlier projects were advanced.