Drainage board approves Lochmuller task order to resume study of previously tabled creek reconstruction

Delaware County Drainage Board · February 11, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Delaware County Drainage Board approved an hourly task order with Lochmuller Group not to exceed $49,200 to study a previously tabled Hog/Paul Creek reconstruction; the consultant will produce a draft in about 45 days and can provide construction-phase services under separate work orders.

The Delaware County Drainage Board approved an hourly task order with Lochmuller Group Wednesday to restart engineering work on a previously tabled creek reconstruction, authorizing study services not to exceed $49,200.

Lochmuller project manager Angie Moyer told the board the task order covers a kickoff meeting and site visit, review of existing data, delineation of drainage areas, hydraulic modeling, two alternatives with exhibits and preliminary cost estimates, identification of potential utility conflicts, a drainage reconstruction report, permitting summaries and a topographical survey. “This is an hourly task order, not to exceed 49,200,” Moyer said.

Board members pressed Lochmuller staff on the technical limits and schedule. Senior engineer Aaron Winger and area manager Anthony Goodnight said watershed delineation would extend beyond the red area shown on the meeting map and that the consultant’s goal is to provide a draft report about 45 days after notice to proceed. Moyer confirmed that services explicitly excluded from this initial task order could be provided later as separate work orders if the board requests construction-phase support such as shop-drawing review, construction administration, inspection and as-built surveys.

The motion to approve the task order was made after the board removed the item from the table; the board then conducted a roll-call vote and approved the task order. No construction contract was authorized at the meeting; the task order authorizes engineering and design work only.

The transcript includes inconsistent naming for the item (the agenda referenced both “Hog Creek” and “Paul Creek” in different places); the board and staff treated the matter as the previously tabled creek reconstruction and agreed Lochmuller will return with deliverables and any recommended next steps. The board did not set a construction schedule at this meeting; further decisions will depend on the consultant’s recommendations, legal review and subsequent board actions.