District facilities director recommends $525,439 roof replacement at Westside Elementary

Sun Prairie Area School District · February 10, 2026

Get AI-powered insights, summaries, and transcripts

Subscribe
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Pete Warwick presented a $525,439 plan to replace seven roof sections at Westside Elementary and recommended awarding the contract to Pioneer Roofing; the item appears on the superintendent’s consent agenda for school board approval.

Pete Warwick, director of facilities and grounds for the Sun Prairie Area School District, presented a proposal to replace seven roof sections at Westside Elementary and recommended awarding the work to Pioneer Roofing. "The proposed roofing project would cost $525,439," Warwick said, noting the item is on the superintendent’s consent agenda because district policy requires board approval for projects above $250,000.

Warwick told the board the district has split roofs into numbered sections to help planning and maintenance and that the proposal covers roof areas 1, 2, 3, 5, 8 and 9 as the base bid, with Alternate Add No. 1 (section 6) shown as a green-option to be added if the budget allows. He said Industrial Roofing Services has been a long-term partner and that both he and the contractor agree "the current asphalt built up roof system should be replaced in the sections identified" because "it is at the end of its service life." Work is planned to begin after the end of the school year and be completed before the next school year starts.

Warwick identified Pioneer Roofing as the lowest bidder and recommended the district proceed with the base bid plus Alternate Add No. 1 for a total of $525,439. He referred board members to a situation report in the board packet for more detail and offered his contact information for follow-up questions. Warwick cited Operational Expectation 12.7 and 6.4 as the procedural basis for presenting the item to the superintendent’s consent agenda.

The transcript records a presentation and a recommendation; it does not record a board vote or formal contract award. The next procedural step is the superintendent’s consent agenda placement for board consideration and any subsequent formal approval.