Purchasing committee opens CMAR RFQ submissions for BOA/forensic center and defers selection for staff review

Rutherford County Purchasing Committee · February 10, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Rutherford County purchasing staff opened nearly a dozen responses to a Construction Manager at Risk RFQ for the BOA/forensic center project, listed the firms that submitted, and the committee voted to take the submissions under advisement for detailed staff review; staff noted one bidder’s license had expired.

Rutherford County purchasing staff opened and listed responses to a request for qualifications (RFQ) for a Construction Manager at Risk (CMAR) to support pre-construction and design-phase services for the BOA/forensic center project. Committee members were read a list of firms and the committee voted to take the submissions under advisement for staff to vet qualifications and compliance.

Staff emphasized the RFQ covers pre-construction services (qualifications and certain service costs) rather than the final construction contract. The committee heard that the procurement will proceed in two steps: (1) pre-construction services to assist cost estimating and design, and (2) later contract award for construction, expected months after pre-construction work.

The record lists firms that submitted qualifications including Century Construction; Arcee Matthews; Rach Young; Cadell; an American firm that previously did public health and safety buildings; Solomon (Nashville); Tucker Group; Carter Group and others. Staff said they will analyze submissions, check compliance with submission requirements, and produce a ranked recommendation for the committee ahead of the next meeting. During the committee’s deep-dive discussion staff flagged that one respondent’s license had expired; members agreed to take the packets under advisement for a later decision and further review.

A motion to take the RFQ submissions under advisement was made, seconded and passed by voice vote. The committee scheduled follow-up review and possible action at a reconvened meeting on March 17.

The RFQ opening and deferral reflect procedural procurement steps; the committee did not take final selection votes at this meeting and directed staff to return with recommendations and a compliance review.