Summary

At the Feb. 5 meeting the town manager outlined a draft CIP that includes vehicle replacements and facility work; staff reported about $8 million in requests with recommended funding nearer $1.7 million and noted a $500,000 grant for a fire truck, leaving roughly $700,000 in local costs for apparatus replacement.

Town Manager Andy and council members used the Feb. 5 meeting to review the draft FY2026–27 capital improvement plan and to discuss tradeoffs among vehicles, facility projects and school safety work.

Andy said department requests totaled roughly $8 million and that the recommended CIP budget currently included approximately $1,677,000 in prioritized items. He noted one favorable development: the town secured a $500,000 grant toward a new fire vehicle but said the remaining apparatus cost to the town is about $700,000.

"We had close to $8,000,000 worth of requests," Andy said, describing how a rolling‑stock replacement schedule and a facilities study pushed many vehicle and building projects into the same near‑term years. He explained that repairs and replacement for public works and emergency apparatus are expensive and driven by industry constraints, regulatory and safety standards, and limited manufacturers.

Council members pressed for clearer alignment between the facility study and the five‑year CIP, noting several facility needs (including Douglas Library items) that do not yet appear in the CIP list. The chair proposed bringing the facilities study to a future meeting as an action item so the public can review the condition assessments and priorities.

Members discussed referendum options, phasing vehicle purchases, contract or bond options and the operational impacts of delaying replacements. Staff said some items that fall under a $75,000 CIP threshold may instead be funded through the operating budget or separately as capital expenses.

The council did not adopt a final CIP at the meeting; members directed staff to present the facilities study to the public, refine estimates and return with a finalized schedule for the Feb. 19 or March 1 meetings to inform the budget process.