Weston planning commission defers storage-facility timeline after neighbors flag uninstalled drainage

Village of Weston Plan Commission and Town of Weston ETZ Committee (joint) · October 14, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The commission deferred a requested timeline extension for Bridal Street Rentals' storage project to Nov. 11, directing the applicant to finish stormwater work (north and south drainage swales and west-side pond) and remaining site items after neighbors reported flooding and missing buffering.

The Village of Weston Plan Commission on Oct. 14 deferred action on a requested amendment to the conditional-use timeline for Bridal Street Rentals' personal storage project after sustained concerns about uninstalled drainage infrastructure and missing landscaping buffers.

In a public hearing and extended discussion, staff outlined the applicant's revised phased schedule that would spread remaining construction through 2025 and into 2026. Neighbors and commissioners said the critical missing element was a continuous north-south drainage swale that, as built, has allowed runoff to flow toward adjacent yards. A neighbor reported water entering property and said planned trees and continuous fencing were not installed as originally approved. Planning staff said portions of stormwater infrastructure and grading either were not installed or were not constructed to plan.

"There is inadequate drainage swale on the north side along the property line," said Roman (staff), who reported observing flooding around the north/east end behind a neighbor's lot and said he had discussed the issue on-site with the developer. Commissioners repeatedly said the drainage must be corrected before winter to avoid further runoff problems.

Commissioners debated enforcement options, including revocation of the conditional-use permit, stop-work orders and tying future permits or building approvals to completion of site work. Several members warned that approving the timeline amendment as-is would signal leniency. "I don't think any of us were aware that that was an issue," said one commissioner, pressing staff on when the drainage expectation was first raised.

The commission ultimately voted to defer the amendment to the Nov. 11, 2024 meeting and attached specific stipulations: the applicant must complete the north and south drainage swales, the west-side retention/detention pond and remaining site work (including fencing and required landscaping access) by Nov. 11. The commission also directed staff to work with the applicant to revise the project timeline to reflect earlier meeting discussions, so the bulk of buildings remain scheduled for completion in 2025 rather than extended into 2026.

The deferral leaves open the question of whether additional enforcement (such as stop-work orders or permit suspensions) will be applied if site corrections are not finished by the deadline. Staff said they would inspect the site and coordinate with the applicant; commissioners asked staff to report back with evidence of the completed stormwater work at the next meeting.

What happens next: The applicant must provide evidence to staff that the required stormwater and site corrections are complete and an updated timeline reflecting the commission's direction. The commission will revisit the amendment at its Nov. 11 meeting.