Staff updates pavilion construction and South Side Park master plan; contingency and intergovernmental funding discussed
Summary
Staff said the pavilion structure is erected but masonry is delayed by weather, three change orders reduced contingency to about $18,031, and planning for South Side Park includes phased utilities, parking, trails and potential amenities with consultant IMEG and intergovernmental coordination.
Unidentified Speaker 4, Unidentified Speaker: Staff gave a multi-part capital update. On the pavilion at the Memorial site staff reported the pavilion structure is erected but weather has stalled masonry; the construction contract total (including change orders) was reported as $973,054 with…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat