Park project updates: change orders reduce contingency; staff outline Phase 2 plans for Prairie Leeward

Urbana Park District · February 11, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff reported three change orders on an existing construction contract, leaving an $18,031 contingency and a total contract value of $973,054; updates included a $10,000 payment to Remco for Kennedy Park demolition, Perkins Road engineering and an outline of Prairie Leeward Phase 2 amenities and potential grant funding.

Staff provided updates on ongoing capital work and near‑term project plans. They said three change orders have been issued for construction work, related to structural foundation adjustments and shop‑drawing revisions; those changes reduced the original contingency of $39,510 to a remaining contingency of $18,031 and raised the total…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans