District updates phase‑2 construction, HVAC audit and auditorium renovation timeline
Summary
District staff reported remaining work to close phase‑2 construction (fire‑alarm punch list, dugout repairs), an ongoing HVAC audit with on‑site walkthroughs, and an auditorium renovation that will require a September–October blackout while major lighting and renovation work proceeds; SED filing is expected in February with permits in spring.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
District capital staff told the board that phase‑2 construction has two remaining punch‑list items (fire‑alarm work and dugout repairs) and that Shaker Flats will return in spring to complete field work. The project director said once those items are finished the district can finalize contract close‑outs and cost reports.
An HVAC audit is underway; consultants will perform walkthroughs with district staff to validate current systems and produce an accurate inventory that matches in‑building conditions rather than relying only on drawings.
On the auditorium project, staff said they intend to submit SED documents in February, expect permits in roughly six weeks, and plan to go out to bid in April with a contract award toward May. Because of the scope of auditorium lighting and renovation work, staff cautioned the facility will likely be unavailable (a "blackout") in September and October while work is completed.
Staff also confirmed that work on baseball and softball dugouts should be complete in time for spring season play. No final contract awards were made at the meeting; staff said they will return with final schedules and cost figures as permitting and bid results are confirmed.