Commission awards plumbing and concrete work to finish Search & Rescue building; bathroom change order approved conditionally

Teton County Board of Commissioners · October 15, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Commissioners awarded rough‑plumbing and a revised concrete slab contract for the county's Search & Rescue building and approved a conditional change order for a temporary bathroom, with funding from sheriff impact fees.

The board voted on multiple construction items for the county Search & Rescue (SAR) building.

Staff recommended awarding the rough‑plumbing contract to Teton West (low bid) for $35,000 to be paid from Sheriff impact fees. The motion passed unanimously. After the plumbing vote staff returned to a revised concrete bid: Affordable Concrete, the low bidder, said additional prep and equipment were necessary; the county approved a change order raising the not‑to‑exceed slab amount to $84,100 (including a $12,500 prep change). Commissioners noted the revised bid remained lower than other bids and approved the award.

Because the SAR group presented that they would occupy the building only if a bathroom were installed, the board also approved a change order to Teton West to build a single temporary bathroom (option 1) for an adjusted contract price of $25,002.62 to be paid from sheriff impact fees. Commissioners conditioned that award on staff verifying the cost to finish both bathrooms in the future and confirming available funding; the formal contract award will be delayed until that review is complete.

Commissioners discussed whether to rebid packages to let one contractor perform both plumbing and concrete to gain efficiencies; legal and procurement constraints about rebidding and lowest responsive bidder processes were discussed and the board accepted staff's recommended awards to the low bidders.