American Fork council approves $1.39 million Auto Mall Drive extension contract to Landmark Excavating
Summary
The council voted to award the Auto Mall Drive extension contract to Landmark Excavating, Inc., for $1,386,402.50 with a $170,000 contingency; council members noted the low bid was roughly $500,000 below the engineer's estimate and cited the contractor's local experience.
Get email alerts on the Contract Award topic
No spam. Unsubscribe anytime.
The council voted to award the Auto Mall Drive extension project to Landmark Excavating, Inc., approving a construction contract in the amount of $1,386,402.50 and a project construction and engineering contingency of $170,000 to be held by the city.
Council discussion noted the apparent low bid was nearly $500,000 under the engineer's estimate, which prompted questions about whether the city should be trepidatious about a low bid. Several council members and staff said they were comfortable with the award because Landmark has completed recent local work — including a bridge at Art Dye and other nearby projects — and is positioned to be competitive on work adjacent to its operations.
Council member Taylor made the motion to award the contract; Council member John seconded. The council conducted a roll-call vote; Ayes were recorded from Council members Hunter, John, Taylor, Holly and Carroll and the motion carried.
The contract was approved as presented, with the city holding a $170,000 contingency for construction and engineering. The chair noted the agenda had reached its end after item 4 was stricken and the council then voted to adjourn.
The contract award obligates the city to the construction contract subject to the terms presented; additional administrative steps will follow to execute the contract and manage the contingency.