Turlock to accept $58,845 TID grant for Montana Park Phase 2; project aims to add courts, playgrounds and ADA surfacing

Turlock City Council · February 11, 2026

Loading...

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council authorized acceptance of a $58,845 Turlock Irrigation District grant for Montana Park Phase 2 and amended the FY25–26 budget; staff described a $4.6 million project adding playgrounds, ADA surfacing, two full basketball courts, nine pickleball courts, and multi-sport courts, with a community meeting planned for Feb. 26.

City staff presented an update on Montana Park Phase 2 and asked the council to authorize acceptance of a $58,845 grant from the Turlock Irrigation District (TID). The council approved the grant acceptance and a budget amendment on a unanimous 5-0 vote.

Staff said Phase 2 will more than double the existing park footprint and include ADA-accessible playground surfacing, a fitness area, two full basketball courts, nine pickleball courts, and multiple multi-sport courts. The total project cost is estimated at about $4.6 million. Funding already secured includes $435,000 from Senator Alvarado and $150,000 from Supervisor Chiesa, with additional grant and funding sources being pursued.

The staff report listed a preliminary schedule calling for 100% design within a month, public advertisement of bids in April, and potential construction start later this year. Staff also announced a community meeting about the project scheduled for Feb. 26 to showcase plans and solicit resident feedback.

A councilmember asked for confirmation of the number of pickleball courts; staff confirmed nine. The council approved the TID grant acceptance and budget amendment to appropriate the funds into the parks project account.

Next steps: staff will finalize design, hold the Feb. 26 community meeting, advertise for construction bids (tentatively April), and return to council with contract awards and further budget actions as needed.