Suamico board greenlights bidding and engineering amendment to advance Well No. 5 project

Village of Suamico Village Board · February 4, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trustees approved bidding the permanent well first and authorized an amendment to the engineering agreement to continue design and bidding for the well station, PRVs and tower; both measures passed unanimously, 7–0.

The Village of Suamico Village Board voted Feb. 3 to proceed with a phased approach to its Well No. 5 project, approving bidding of the permanent well ahead of the facility, PRVs and tower and authorizing an amendment to the professional-services agreement to complete design and bidding for the remaining components.

Director (transcript name variants) told the board the recommended approach is to drill the permanent well and analyze water capacity and quality before finalizing the facility design. That sequencing, the director said, allows staff to confirm treatment parameters and then complete the facility design and bid packages. He said design documents will be submitted to the Wisconsin Department of Natural Resources for plan approval and to participate in the Safe Drinking Water Loan Program.

The director said a DNR-required pilot test for treatment parameters is expected to cost about $40,000 and is scheduled to begin in March or April. The board discussed funding and rate impacts: the director said the project will likely be funded partly with impact fees (approximately 40% of the plan) and that utility-rate increases would likely be staged in 2026 and subsequent years per Public Service Commission (PSC) timing.

Trustees approved two separate motions: one to bid permanent-well construction now (motion passed 7–0), and one to approve Amendment No. 2 to the Ayers and Donahue / Arizona Associates professional-services agreement to continue design and bidding for the well station, PRVs and tower (motion passed 7–0). Staff said construction is targeted to begin in 2026 depending on contractor availability and DNR approvals.