Nueces County approves change order for Bob Hall Pier after questions about contractor work and budgeting
Summary
Nueces County Commissioners unanimously approved Change Order No. 4 to the Callan/Cal Marine contract for Bob Hall Pier, adding decking, ADA ramp work and other items; commissioners pressed staff on prior change orders and contractor practices and agreed to take some questions into executive session.
The Nueces County Commissioners Court unanimously approved Change Order No. 4 to the Callan (Cal Marine) contract for the Bob Hall Pier project after staff described additional decking, ADA ramp adjustments and gap-filling work that was outside the contractor’s original scope.
County construction staff told the court the changes were vetted and would extend the pier’s lifespan. "This is work that was researched. It was vetted. We checked costs. We evaluated the contractor's proposals to do this work," a county construction manager said during…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat