Committee advances Bray Park restroom construction, defers playground and pavilion to reduce duplication and cost

Marshfield Parks, Forestry & Recreation Committee · February 12, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff proposed and the committee approved a phasing change for Bray Park redevelopment: advance the $315,000 restroom project and defer a $115,000 playground and $210,000 pavilion from 2026 to 2027 to avoid duplicate utility work and keep the overall completion target of 2028.

Staff presented a recommended phasing adjustment for Bray Park redevelopment to improve financial efficiency and reduce redundant construction work while maintaining a 2028 completion goal.

The phasing table in staff's memo listed completed and planned work: pickleball courts ($650,000; completed 2024), softball ($295,000; completed 2024), playground ($115,000; scheduled for 2026), pavilion ($210,000; scheduled for 2026), and restroom ($315,000; scheduled for 2027). Staff recommended advancing the restroom construction into 2026 and shifting the playground and pavilion to 2027 while keeping funding levels unchanged.

Staff said the existing restroom/pavilion sits in the footprint of the proposed playground and acts as a central utility hub (electric, water, sanitary). Advancing the restroom avoids temporary utility connections, re-excavation and duplicate work; staff also said using a modular restroom (precast unit delivered and set) could reduce weather risk and speed installation. Committee members discussed tradeoffs, noting the playground would be delayed a year but the restroom is heavily used by park users (pickleball, softball, disc golf) and tearing it down without replacement would be disruptive.

A committee member moved to approve the revised phasing; the motion was seconded and approved by voice vote.

Next steps: staff will pursue modular restroom procurement and coordinate timing with playground design and other CIP adjustments; formal CIP and budget amendments will be processed through the usual council and board actions.