Middle Peninsula briefs Middlesex on Broad Creek dredge, regional dredging authority and next steps
Summary
County and Middle Peninsula leaders said federal and state funding is limited but a newly capitalized Public Access Authority and regional dredging plans offer a path to predictable maintenance; the board authorized short-term contractor-use policies and asked staff to pursue permitting and phased dredging options.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Regional planners and consultants told the Middlesex Board of Supervisors on Aug. 5 that Broad Creek's recent dredge removed roughly 36,000–37,000 cubic yards, and that the Middle Peninsula is pursuing a larger municipal dredging program to break the recurring cost cycle.
Louis Lawrence of the Middle Peninsula Planning District Commission described a $7.5 million allocation now held by the Middle Peninsula Chesapeake Bay Public Access Authority to operationalize a regional approach. He and others described financing tools under study, including service districts and tax-increment-like mechanisms, and said local participation will determine which localities join a "coalition of the willing." Rebecca Francis, a coastal scientist, gave technical details of the Broad Creek project and noted disposal constraints that reduced initial dredge depths but still exceeded expectations.
The board authorized immediate use of a revised contractor-use policy for the Broad Creek spoil site and approved staff authority to advertise an RFP for long-term spoil-site management. Separately, staff and consultants briefed the board on Carlton Road (Mill Creek) dredging options: a near-term "band‑aid" Corps resubmittal to clear the ramp versus a longer-term redesign of a sediment basin and jetty extensions to enable commercial harvesting. The board asked staff to pursue a Corps resubmission and to continue parallel design work and contractor outreach so that a sustainable maintenance model can be developed.
Board members emphasized the need to balance recreational and commercial uses and to ensure any dredging package has an identified disposal strategy. Staff were directed to return with cost estimates, permitting steps (JPA/Corps), and grant opportunities to fund both short-term and longer-term solutions.