Superintendent: high-school construction on track; traffic study and ribbon-cutting forthcoming
Summary
District superintendent reported foundations and plumbing progressing, pre-bid contractor interest for high-school work, a pending traffic study to guide site circulation, and an operation center ribbon-cutting slated for Feb. 9.
Get email alerts on the School Construction topic
No spam. Unsubscribe anytime.
At the Jan. 27 meeting, the superintendent provided an update on the district’s multi-phase construction work and near-term milestones.
The superintendent said plumbing approvals are complete and foundation work on the south end is underway. Contractors showed strong interest at a recent pre-bid meeting for the high-school scope, and the district expects to have bid numbers by the next board meeting or may call a special meeting in March to keep the schedule. “We should have numbers coming here by the next board meeting and probably for Google. If not, we may have to have a special meeting, in probably March,” the superintendent said.
The board heard the construction schedule will phase work to limit disruption: one summer will focus on the gymnasium and performing-arts areas, another on classroom wings, with HVAC and flooring upgrades staged to avoid interrupting core academic spaces. The superintendent also described planned parking-lot milling and new lighting and said separating bus and parent circulation could yield roughly 100 additional parking spaces by reallocating bus staging.
A traffic study for the high school is pending; the superintendent said the study will guide placement of bus access, student and family drop-off zones and potential one-way flows coordinated with the city and engineers. The superintendent also announced a ribbon-cutting for the operation center on Feb. 9 at 9:30 a.m.
The administration agreed to post project maps and renderings publicly as they become available and to provide ongoing progress information to the community.