Council approves Lafayette Street Connector plans and budget amendment

City of Broussard Council · February 10, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Como Engineering presented reconnection plans for Lafayette Street to Main Street, with intersection geometry changes, Madison to be disconnected as a through street, and anticipated engineering completion in a few months; council approved budget amendment to proceed.

Broussard council approved funding to advance the Lafayette Street Connector project after hearing from Walter of Como Engineering. Walter explained the plan to reconnect Lafayette Street to Main Street, modify intersection geometry, and convert an existing through street (Madison) to a non‑through configuration to support new City Hall parking and pedestrian access. He said the city now owns the old school and the linkage will provide access and parking options; minor drainage and grade work may be required.

Walter indicated the engineering work could be completed in “a couple of 3 months” after council direction and that temporary signage had been placed earlier that day. Council members approved the budget amendment to allow engineering and initial work to proceed.