Board approves $145,000 change order for wastewater plant; contractor time extension included
Summary
The Board approved construction change order No. 4 for the wastewater treatment plant, roughly $145,000 and a 154-day schedule allowance; staff said many items addressed operator health-and-safety issues and unexpected work found under covers and roofs.
Get email alerts on the Wastewater Plant topic
No spam. Unsubscribe anytime.
The Board of Public Works approved construction change order No. 4 for the wastewater treatment plant project, an approximately $145,000 increase staff said addresses 17 additional items identified by operations personnel.
Roger told the board the extras include safety-related items (stairs where staff had been using ladders), temporary blower hookups while units were repaired or repositioned, and cleanup associated with flood-related mud and damaged equipment. Staff said many items were not visible until the contractor opened covered areas and that several items were judged necessary for safe, long-term operation.
The item includes an incorporated schedule allowance of 154 calendar days, largely tied to electrical equipment shipping and related sequencing; staff said the additional time was priced into the change order and should not trigger further cost claims. Board members requested more transparent time-and-materials detail for certain line items; staff agreed to provide contractor-level breakout and invoices in future change-order packets.
A motion to approve was made and carried by voice vote. Staff said some remaining roof/structural repairs will proceed as an insurance claim and a separate punch list (digester roof work was noted as carrying into summer).