Summary

A presenter outlined a plan for a standalone recycling and organics recovery facility (about 55,000 sq. ft., roughly 3½ acres) that would serve Rollins and neighboring communities. The project team said eight towns have expressed interest and that Sinclair refinery and other funders could help under a public–private structure.

A project team told the Rawlins City Council on Dec. 7 that a proposed regional solid‑waste recovery and organics treatment facility could be built on city‑owned land offset from the existing landfill and would focus on recyclables and organics, not demolition or bulk construction debris.

"The facility would be a 55,000‑square‑foot facility," the presenter said, and added the site would likely need about "3 acres and a half." She told the council her team has met with at least eight nearby communities that have signaled interest and said letters of support are expected.

The presenter said the team is pursuing public‑private partnership structures and has consulted legal experts on contract models that would define roles and limit city liability. "We want to be clear that we want everybody to understand what the goals and responsibilities are, to minimize any legal problems that might crop up," she said.

Council members asked where the plant would sit relative to the transfer station and landfill; staff and the presenter clarified the parcel is city‑owned and the facility would be offset to the northwest of the current transfer station, not directly on the landfill footprint.

Cost and financing remain unresolved. The project team said detailed capital and operating numbers will be available after equipment bids, but pointed to potential savings from reducing hauling to Casper: staff noted the city currently budgets roughly $300,000 for hauling to Casper and another ~$225,000 in professional services for landfill operations, suggesting localized processing could reduce out‑of‑town disposal costs.

Council members raised standard concerns about road upgrades for heavy truck traffic and asked how the facility would handle recyclables vs. residual waste. The presenter said clean recycling operations would remain in town and that the new facility would accept recyclables and organics for sorting and processing. "We're just looking at the organics, household—anything that's recyclable," she said.

Next steps: Council members asked staff to provide more detailed cost estimates, contract templates, and traffic/ingress recommendations. The project team committed to follow up with the requested figures and to deliver letters of support collected from interested communities.