Engineer: punch-list walkthroughs set; Lift Station 6 expected to resume by May or June
Summary
Westler Engineering reported punch-list walkthroughs with contractors and operators, with phases 1 and 2 nearing completion; Phase 2b (Lift Station 6) should restart after snow melt and be operational by May or June.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
Katie Jackson of Westler Engineering updated trustees on construction progress, punch-list scheduling and the timeline for Lift Station 6.
"The project continues to move forward," Jackson (Speaker 3) said, noting scheduled punch-list walkthroughs with the contract operators and contractors in the coming weeks to narrow outstanding items for phases 1 and 2. She described Phase 2b (Lift Station 6) as paused for winter conditions but expected to resume once the snow melts and "should hopefully be up and running by about May or June."
Trustees did not alter the construction schedule at the meeting. Jackson said the walkthroughs are intended to reduce outstanding items to just a few finish tasks so staff can focus on final inspections and closeout steps.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.