Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Council told Coal Creek contract needs $210,000 change order for alternate rock source

Cedar City Council · May 1, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff said the Coal Creek EWP project requires a change order because the originally planned rock failed NRCS testing; the contractor identified an alternate source that raises haul and processing costs, increasing the contract by an estimated $210,000 to supply about 7,000 cubic yards. Staff said NRCS funds would cover the additional cost and the city does not expect extra city dollars.

City staff told the council that Change Order No. 1 for the Coal Creek EWP project is necessary after planned rock failed to meet NRCS standards.

A staff presenter said the contractor located an alternate rock source that must be…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans