Hancock County approves Texas Flat Road reconstruction; notice to proceed Oct. 24, work begins Oct. 27

Hancock County Board of Supervisors · October 20, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Board approved a notice to proceed for Texas Flat Road reconstruction to Huey Stockstill, set a notice date of Oct. 24 and work start of Oct. 27 with single‑lane closures, and authorized four subcontractor payments totaling roughly $140,091.30.

County staff presented a notice to proceed for reconstruction of Texas Flat Road (STP project numbers 112600002 and 109415701000) to contractor Huey Stockstill. The board approved the notice to proceed, with a staff-stated notice date of Oct. 24 and work beginning Oct. 27; staff said initial work will include single-lane closures with flaggers.

The board also approved four subcontractor requests related to the reconstruction: Gulf Coast Solutions ($39,500), Road Pro Safety ($13,302), JL McCool Contractors ($76,139.30) and A1 Ceiling ($11,150). Staff described subcontract scopes (erosion control, traffic safety/signage, general masonry/site work, joint ceiling) and noted rumble strips and striping were included in the plan. Supervisors said the in-house rental and subcontracting approach is more economical than prior contractor arrangements.

A motion combining items 2 through 5 for the project passed unanimously (5-0). Staff said the notice to proceed will prompt sign installation and that single-lane traffic control will be used at the project openings. The board recorded no conditions on the approval beyond standard bond and insurance checks.