Palm Desert unveils two-concept plan for new municipal library at Parkview site with $20M and $30M budget options
Summary
City staff and Richard Kennedy Architects presented low- and high-budget conceptual designs for a new Palm Desert municipal library on the Parkview site (options ~17,000 sq ft/$20M and ~26,000 sq ft/$30M); the county provided $4,000,000 and staff plans to return with appropriation requests and schematic designs aiming for occupancy in 2027.
Get email alerts on the Public Infrastructure topic
No spam. Unsubscribe anytime.
City staff and the selected architect presented two conceptual designs for a new Palm Desert municipal library and said the library advisory committee unanimously recommended building a new facility on the Parkview (former Sheriff Station) site.
Ryan Lamb, capital projects, reviewed the project history: the council formed a library task force in June 2023 and voted in September 2023 to withdraw from the Riverside County library system and self-operate beginning July 1, 2024. Lamb said the city and county negotiated a withdrawal agreement that included $4,000,000 from the county to support development.
Architect Lee Swanson of Richard Kennedy Architects described a high concept (designed to a $30,000,000 budget, just under 26,000 square feet) and a low concept (designed to a $20,000,000 budget, just under 17,000 square feet). Swanson said the high option includes traditional stacks, meeting spaces, a maker lab, demonstration kitchen, dedicated visitor center and cafe, and flexible multipurpose areas; the low option reduces program elements to meet the smaller budget.
Swanson explained the design intent: a building that references regional palm-grove imagery with a shading canopy, shaded exterior program space integrated with Civic Center Park, large north-facing windows to reduce heat gain, durable materials, and flexible low-height book stacks to preserve sight lines and safety.
On funding and schedule, Lamb said the city has used the county's $4,000,000 for initial consulting and surveys and that staff anticipates bringing appropriation requests this fiscal year for the remaining budget depending on whether the council selects the $20M or $30M concept. He said demolition of the Parkview building is included in the construction estimate and staff hopes to move into schematic design after council approval of a conceptual design; the team said the new facility could be occupied by 2027 if the schedule holds.
Council members praised the environmental-focused design choices and asked clarifying questions about demolition costs, remaining Parkview cash, potential use of leftover RDA funds versus Measure G, and maintenance responsibilities under the College of the Desert lease. Lamb said the lease covers routine maintenance and that staff are negotiating repair/replacement timing with COD; if replacements are needed, staff said they have budget thresholds and reimbursement arrangements to address urgent items.
What happens next: staff asked for conceptual-design approval at an upcoming meeting, then will move into schematic design and the entitlement process (planning commission and architectural review), prepare bridging documents for an RFP for design-build, and return with appropriation requests this fiscal year.