Council approves $190,450 engineering agreement for Rogers Road well design
Summary
The council authorized an agreement with JUB Engineers for $190,450 to design the Rogers Road public well house and oversee bidding; staff said the project (well plus salt shed and pipeline) is expected to take about two years from design through construction.
Get email alerts on the Infrastructure Water topic
No spam. Unsubscribe anytime.
Tooele City Council voted unanimously on Jan. 21 to approve Resolution 2025-92, authorizing a professional engineering services agreement with JUB Engineers, Inc. for design and bidding services for the Rogers Road public water-supply well house and a salt shed.
Public Works Director Jamie Grandpre described the action as a continuation of prior test drilling at two sites and said the team plans to move one site from test-well to production. Grandpre told the council the contract with JUB covers full design and bidding oversight and cited a contract amount of $190,450. He said design is expected to take roughly six to nine months, with construction taking another six to 12 months (overall, about two years from design start to a completed, operating well).
Council members asked about construction timing and whether a storage tank would be required for chlorine contact time; Grandpre said the preference was to run a pipeline rather than add a storage tank but that the design phase could identify different needs. Grandpre also said each new well project is planned to include a generator.
Councilman Hansen moved to approve the resolution; Councilwoman Gochis seconded. The motion passed 4-0.
The agreement moves the Rogers Road well project from testing into formal design and positions the city to solicit construction bids following completion of JUB's design work.