Herriman staff present schematic for new public works facility with first-phase cost estimate of roughly $18.4 million

Herriman City Council · November 13, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff presented a two‑phase public works facility plan centered at Butterfield Park: Sequence 1 (administration ~18,000 sq ft and fleet ~10,000 sq ft) has an estimated construction cost of about $13 million and total with contingencies/soft costs around $18.4 million; Sequence 2 is estimated at $10–15 million. Council asked to consider CIP inclusion and staged construction.

Justin, public works staff, presented a schematic needs assessment and two‑sequence plan to expand and consolidate the city’s public works functions at Butterfield Park. He said sequence 1 would include an administration building of roughly 18,000 gross square feet and a fleet building of about 10,000 square feet, with total construction estimated at about $13,000,000; contingencies and inflation pushed the figure to roughly $17,000,000 and, after soft costs (architecture, furniture, IT, testing),…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans