Council awards Herriman Community Center remodel contract with reduced scope, seeks extra grant funds
Summary
Bids for the Herriman Community Center remodel came in above budget; council authorized a not-to-exceed contract for a reduced scope with Gladwell Construction and added a provision allowing staff to restore original scope if pending grant funds arrive.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The Herriman City Council voted June 11 to award a construction contract to Gladwell Construction for a reduced-scope remodel of the Herriman Community Center after bids exceeded available funds.
Justin (staff) told the council the combined FY25 and anticipated FY26 budget for the project is just under $430,000 (including a $135,000 CDBG grant expected in FY26). With design costs (~$55,000) and other allocations, roughly $374,000 remained for construction. Bids came in at about $510,000; to align the project with the available construction budget, staff and the low bidder revised the scope and removed the ADA ramp work (an item Justin said amounted to roughly $110,000) while preserving HVAC, electrical, energy-efficiency improvements and the security divider wall.
Justin asked the council to award the contract to Gladwell Construction under a not-to-exceed amount matching the available construction budget and to permit staff to issue a work directive and change order to restore bid-alternate work if additional grant funds are received. Councilmember Jared moved to approve Gladwell Construction with a not-to-exceed value of $374,390 and amended the motion to explicitly allow staff to complete the original scope if grant funds materialize; the amended motion passed on recorded ayes.
Staff said they expect a county grant decision in July and that, if awarded, the additional funds could be added by change order rather than re-bidding. Council members asked staff to return any funding acceptance for budget amendment as required by standard procedures before those funds are spent.
Background and budget detail - Total design cost: approximately $55,000 (covered partly by county funds). - FY25 budget: just over $294,000; FY26 CDBG grant added $135,000, giving a combined budget just under $430,000. - Construction funds available before award: roughly $374,000. - Low bid(s) and alternates: combined base bid + alternates came in about $510,000. - Revised contract: not-to-exceed $374,390 for the reduced scope; ADA ramp (~$110,000) removed from the current contract but may be added later via change order if additional funds are secured.
The council’s vote authorizes staff to proceed with the construction contract while retaining flexibility to expand the scope if grant funds are confirmed.