Commission recommends repair of historic downtown building at 5026 Highway 140, flags CEQA review if major work found
Summary
The Mariposa County Historic Sites and Records Preservation Commission voted unanimously to recommend approval of exterior repairs at 5026 Highway 140 (DIS202500059), while adding a condition that significant, unforeseen alterations discovered during exploratory siding removal may trigger California Environmental Quality Act (CEQA) review.
Get email alerts on the Historic Preservation Repair topic
No spam. Unsubscribe anytime.
The Mariposa County Historic Sites and Records Preservation Commission on Jan. 12 recommended that the planning director approve a partial exterior repair and maintenance project at 5026 Highway 140, a contributing historic structure in the county’s historic design review overlay.
Planner Elijah Banda told commissioners the work — identified as DIS202500059 — would remove siding for inspection, replace damaged framing as needed, re-side the northeast, southeast and northwest walls with fiber-cement lap siding (HardiePlank, colonial revival tan), re-roof small portions with standing-seam metal in a rustic red color, and repaint trim in a medium brown. Banda said staff will include “a finding that this project is exempt from environmental” review in the recommendation but added a condition requiring further CEQA analysis if exploratory work finds repairs or alterations that would raise environmental review questions.
Applicant Andrew Van Wyhee described the priority as stabilizing the building’s deteriorated side walls and getting the structure watertight. “I think our main priority right now is just to address the sides of the structure that are in really bad shape and just keep it from deteriorating any further,” he said during the meeting.
Commissioners asked whether work to the front façade was included; staff and the applicant confirmed no front-facing changes are proposed under the current application and that any future façade alterations would require a new design review. Commissioners also welcomed the use of fire-retardant materials for siding and roofing as a safety improvement for downtown.
A commissioner moved to recommend approval as presented with the standard requirement that any additional work outside the approved scope return for review; the motion was seconded and passed unanimously. Staff told the applicant the next step is to obtain a building permit.
Authorities and conditions referenced by staff include the county’s historic design review standards and the California Environmental Quality Act. The commission’s record of the vote appears in the meeting minutes; staff will forward the commission recommendation and the CEQA-trigger condition to the planning director for final action.
The planning director’s decision and any subsequent permit application materials will determine whether additional environmental review is required and whether further design review hearings will be needed.