The council voted unanimously to adopt Resolution 26‑01, granting perpetual easements to UDOT (to be transferred to the U.S. Bureau of Reclamation) for secondary water lines relocated during the US‑89 project; staff said the city will continue operating the system under the existing arrangement.
Get email alerts on the Infrastructure Easements topic
No spam. Unsubscribe anytime.
Layton City Council voted unanimously on Jan. 15 to adopt Resolution 26‑01, authorizing the city to grant perpetual easements to the Utah Department of Transportation so UDOT can transfer them to the U.S. Bureau of Reclamation in connection with the US‑89 Farmington to I‑84 corridor project.
Steve Jackson, city staff, said the easements cover three locations where secondary water lines owned by the Bureau of Reclamation were relocated during construction. He described the action as a required formal step following completion of the highway work: "This is just the formal action by the council to grant these easements," Jackson said.
Jackson and engineers confirmed the city’s engineering division and the city attorney’s office reviewed legal descriptions and concluded the documents are in order. Council staff clarified that although the Bureau of Reclamation owns the pipe, the Weaver Basin system and the city operate the secondary water service. "We operate the secondary water system for Weaver Basin," a staff speaker said, noting the grant of easements will not change who operates the water service.
The easement locations referenced in the presentation include the corridor near 2130 North, 2900 East, Marvin's Way/Dreams End and 1985 Valley View Drive on the east side of the highway. Staff described these as service and secondary water lines that need recorded easements to protect them in perpetuity.
Council Member (speaker 2) moved to approve Resolution 26‑01; a second was recorded and the motion passed without opposition. The mayor announced the resolution passed with a unanimous vote.
Next steps: Staff will finalize documents and the mayor was authorized to sign the necessary easement instruments so UDOT can complete its transfer to the U.S. government and the Bureau of Reclamation.