Council reviews $18 million schematic for new public works campus; staff to consider phasing in CIP

Herriman City Council · November 13, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff presented a public works facility needs assessment proposing a two-sequence plan (administration + fleet first) with Sequence 1 construction estimated at about $13 million and a Sequence 1 total of roughly $18.4 million after contingencies and soft costs; council discussed phasing, cost per square foot and CIP timing.

Herriman — City staff presented a schematic needs assessment and site plan for a consolidated Public Works campus at Butterfield Park and outlined estimated costs, phasing and operational benefits.

Justin (Speaker 7) said the design team used previous GSBS baselines and on-site visits to comparable facilities to define programmatic needs. The plan separates work into two sequences: Sequence 1 includes an administration building (roughly 18,000 sq ft combined program area) and a fleet building (about 10,000 sq ft).…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans