Councilor update: Buckley Draw construction paused, Slate Canyon conservation talks continue, Ironton redevelopment in early review
Summary
Councilor Jeff briefed the East District on paused Buckley Draw construction pending debris-channel completion, ongoing Slate Canyon conservation-easement talks, and an early-stage Ironton redevelopment general-plan amendment; residents raised water, traffic and affordable-housing questions.
Get email alerts on the Land Use And Development topic
No spam. Unsubscribe anytime.
City councilor Jeff updated the East District on several development and conservation matters affecting the neighborhood, drawing questions about water, traffic and housing outcomes.
Jeff said Buckley Draw construction is paused while the debris channel is completed to design standards; Rocky Mountain Power and the city are coordinating, and the city will withhold building permits until the channel meets standards. When approvals occur, staff estimated about 30 days to finish channel work before construction resumes.
On Slate Canyon, Jeff said the city and partners (including Utah Open Lands) met and plan additional public forums to explore a conservation easement that would keep much of Slate Canyon protected while possibly allowing a roughly 20-acre park on city-owned land. Jeff described the conservation easement as a community-driven tool to preserve land in perpetuity and said more public discussion is coming.
Aaron Ardmore, development services planning manager, described the early-stage Ironton redevelopment application now in staff review: a general-plan amendment from industrial to mixed-use, a pending zone-map amendment, and a concept plan showing about 90 condos, 65 townhomes and roughly 16,000 sq ft of commercial space. Ardmore said staff advised alternative zoning tools because the mixed-use zone may not fit the proposed plan; next steps include revised plans, further staff review, planning commission hearings and then city council consideration.
Residents raised questions about water availability for new development during a drought, the role of tax-sharing with Springville for the mixed-use corridor, affordable-housing requirements or deed restrictions (CC&Rs) to encourage owner-occupancy, and traffic impacts along State Street. Ardmore said water, sewer and infrastructure capacity are part of staff review and that a traffic study will be required before public hearings.
A public comment also flagged an upcoming planning commission hearing on proposed data centers and encouraged residents concerned about water and electricity demands to attend the March 3 council meeting.