West Valley seeks contracts, donations to finish Veterans Memorial Phase 2 before June 30 match deadline
Summary
Staff reported receipt of a $524,715 phase‑1 match from Salt Lake County TRCC and seeks completion of Phase 2 to secure a remaining $399,125 by June 30. Phase 2 includes a Navajo Code Talkers statue and WWII plaques; staff negotiated with EDA Architects and Oakland Construction to lower costs and noted an LDS Church donation of granite.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Mr. Arslanian combined presentations on Resolutions 25‑67 and 25‑68 to describe Phase 2 work for the Veterans Memorial and to request authority to proceed with negotiated agreements.
He said the city has received $524,715 for the phase‑1 match from Salt Lake County TRCC and needs to complete Phase 2 to receive the remaining $399,125 by the June 30 deadline. Phase 2 will add World War II elements including a Navajo Code Talkers statue (described as larger than life), a large WWII airmen monument and a Normandy landing plaque.
Arslanian described negotiations with EDA Architects and Oakland Construction, noting both provided concessions from earlier proposals; Oakland had bid around $2.6 million earlier and staff worked to reduce costs through supplier negotiations. He said EDA donated a $28,000 fee deduction and that the Church of Jesus Christ of Latter‑day Saints donated stone estimated at roughly $10,000–$15,000 to the project.
Councilmembers asked for site plan graphics and details about how Phase 2 ties to Phase 1; staff said they would circulate images and noted the addition would be a seamless continuation of the existing memorial. Staff emphasized the timing pressure to meet the June 30 match deadline and described ongoing fundraising through the veterans committee.
No formal contract award vote is recorded in the study session; staff requested council approval to finalize agreements so construction can begin promptly if council directs.