City requests $40 million more for waterfront flood mitigation; staff says bulkhead replacement and pump station needed

Alexandria City Council · February 26, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City presenters asked council for an additional $40 million for waterfront flood mitigation to replace failing bulkheads in core segments and to fund a pump station to drain areas behind raised bulkheads; staff cited condition assessments and sea‑level‑rise projections.

City staff asked council for an additional $40,000,000 for the waterfront flood mitigation project, citing deteriorated shoreline conditions and the opportunity to advance technically preferred concepts in the core waterfront area.

"We are asking for an additional 40,000,000," the waterfront presenter said, explaining that the funds would allow bulkhead replacement in the core segment from Duke Street through Waterfront Park and permit future proofing for higher elevations as sea level rises.

Staff described recent condition assessments that show core segments — especially the Waterfront Park bulkhead and promenade — have declined to "poor to critical" condition ratings and said earlier cost ranges for the full project were previously estimated at $250 million to $350 million when including the marina and northern segments.

On engineering interaction between components, staff explained that raising the bulkhead height without improved drainage would create a basin where stormwater collects. "That necessitates, the pump station as well to address that stormwater infrastructure and pumping, as well as any riverine flooding so we could recover quickly after a flood," the presenter said.

Councilmembers asked about design choices, potential revenue opportunities from piers, and grant pursuit. Staff said they have pursued federal, state and other grants and will continue to seek funding partnerships; the presentation concluded with staff offering follow‑up slides and details for council questions.