City staff recommends $741,344 resurfacing contract to Barrett Paving

Vandalia City Council · February 16, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public works recommended awarding a 2026 street-resurfacing contract to Barrett Paving Materials at $741,344.52 with a 10% contingency; staff said combined curb, sidewalk and resurfacing work remains about $216,136.79 under the 2026 budgeted amount of $1,463,000.

Public works staff recommended awarding the city's 2026 street resurfacing contract to Barrett Paving Materials for $741,344.52 and adding a 10% contingency to cover potential changes or extra work.

At the March study session, Mr. Borton said three bids were received for the resurfacing program, ranging from $741,344.52 to $853,208.10, and described the work as following the curb-and-sidewalk program. He said the combined budget for curb/sidewalk, trip-hazard removal and resurfacing in 2026 was $1,463,000 and that, after current estimates, the combined program would be about $216,136.79 under budget, which is why staff recommended a contingency to allow adding streets or other work.

Council did not take a formal vote in the study session transcript; Borton presented the recommendation to the council for formal action at a later meeting. The transcript lists the engineer's estimate as "$82,000," a figure that differs materially from the received bids; that discrepancy is noted here as reported in the transcript and should be verified with the city engineering office before publication.