Davis Camp dock, launch ramp completed under budget, Mohave County staff report

Mohave County Board of Supervisors · February 15, 2026

Summary

Public Works reported the Davis Camp dock and launch ramp ARPA project reached substantial and final completion ahead of schedule and under a total cost of $460,554; staff credited the contractor and in‑house project team for meeting Army Corps dredging timelines.

Mohave County public works staff reported on Feb. 17 that the Davis Camp dock and launch ramp ARPA project reached substantial completion ahead of schedule and under budget, with total project costs reported at $460,554.

Director Letovsky and project staff credited Lewis Construction and county construction inspector Steve Walker for staying on schedule and coordinating dredging and prefabricated dock lead times. The project included a reconstructed walkway, new utility poles and a prefabricated floating dock and launch ramp; staff said the floating dock design may be informative for future South Cove improvements, where water levels vary seasonally.

Supervisor Martin asked for project documents to take to an upcoming meeting with Lake Mead partners and staff agreed to provide design and performance information that afternoon.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source