Utility Board approves substation maintenance and temporary power device; directs rebid for Walker Substation labor
Summary
The Lawrenceburg Utility Board approved a $39,237 preventive maintenance contract for Ludlow Hill Substation, a $5,274 temporary power restoration device, and authorized staff to re‑bid the Walker Substation labor portion with an updated estimate after initial quotes far exceeded earlier estimates.
Utility Director Rob Schneider presented three operational items to the Utility Board. Schneider said Quala Solutions, previously approved for substation maintenance, submitted a quote of $39,237 to provide preventive maintenance at Ludlow Hill Substation covering regulators, transformers, breakers, relays and meters; the board moved and approved scheduling that work for spring.
On emerge…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat