County discusses gravel stockpiles, crushing options and new road-stabilization trial

Winnebago County Board Meeting · February 18, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Secondary Roads staff updated the board on material inventories (Sunnyside ~30–35k tons; Lewis ~15–20k tons), options for contracting crushing services, and plans to trial a chemical stabilizer ('glue') on select roads.

County secondary roads staff briefed the board on stockpiles, crushing options and a potential trial of a road-stabilization chemical.

Staff said Sunnyside currently holds roughly 30,000–35,000 tons of material and Lewis about 15,000–20,000 tons; they expressed a preference to avoid moving material more than necessary and suggested seeking options to blend lower-spec granular material economically rather than discarding it. "So I'd like to see 10,000 tons there," staff said about a new yard to hold material.

The board discussed procurement options for crushing: counties can lease a pit and arrange crushing, or the landowner can contract with a crushing company and sell a pile to the county. Staff said the county will evaluate both approaches and possible third‑party arrangements to maximize usable material and manage costs.

Separately, staff described a trial 'glue' or chemical stabilization treatment for certain road segments (North Rice Lake Road was mentioned) that requires logistical planning; the treatment sets up quickly and may allow work to occur under traffic with limited disruption.

Members reported local concerns such as possible tile/blocking issues affecting a stretch of 150th North of Vinje; staff agreed to inspect the site. Commissioners and staff also noted that recent stop-sign installations (Scargill) and rumble-strip monitoring have shown increased compliance at some intersections, though camera-based enforcement is limited.

No formal decisions were taken during the operations updates; staff will continue to estimate tonnage, evaluate crushing contracts, and plan the stabilization trial.