Diversion reaches connected, Rush River cut over; bridges and crossings advancing

Metro Flood Diversion Authority Board · January 23, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff reported interim completion of multiple channel reaches, the Rush River was cut over into the diversion channel, bridge work and BNSF track installation continue, and County Road 22 and other cutovers are expected in the coming weeks to months.

Staff reported multiple near‑term construction milestones that move the diversion project toward operational connectivity in several northern reaches. Paul, standing in for the construction lead, said interim completion has been reached on several segments and that "the Rush River has been cut over into the diversion channel," meaning water in that corridor can flow down the diversion to the Red River.

Detai…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans