Council approves $1.045 million change order to extend sewer work for Smoky Point Boulevard roundabout project
Summary
Council approved change order number 2 to extend an 18‑inch sewer main about 1,090 feet to Lift Station 6, increasing the project cost by $1,045,696.05; staff said the work will be funded from the Sewer Capital Improvement Fund.
The Arlington City Council approved a contract change order that expands sewer work associated with the Hundred And 88th and Smoky Point Boulevard roundabout project, increasing the project cost by $1,045,696.05.
Public works staff described the change order as an upsizing of an existing 8‑inch sewer to an 18‑inch main and an extension of roughly 1,090 feet to reach Lift Station…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat