Council approves phased Las Palmas Park revitalization to use Proposition 68 grant funds
Summary
Facing higher construction estimates, council approved a phased approach for Las Palmas Park that advances high-impact Phase 1 improvements (playground, ADA upgrades, fitness equipment) within available Proposition 68 funds and seeks grant funding for Phase 2.
Get email alerts on the Parks And Recreation topic
No spam. Unsubscribe anytime.
The City Council approved a phased approach for the Las Palmas Park revitalization project so work can begin on priority improvements within available Proposition 68 grant funding.
Public Works staff said the city received a $4.2 million Proposition 68 grant; about $531,000 has been used for design and outreach, leaving roughly $3.7 million for construction. Construction estimates for full build-out rose to roughly $10.2 million due to inflation and market conditions. To avoid delaying all improvements, staff proposed splitting the project: Phase 1 will deliver playground upgrades, ADA accessibility improvements, modernized fitness equipment, renovated picnic areas and lighting; Phase 2 will complete fields and broader site work when additional funding is secured.
Staff emphasized Phase 1 is designed to integrate into the final build and would not preclude Phase 2. Councilmember Solorio recused from discussion for a proximity-related conflict and the council approved proceeding with Phase 1 with direction to coordinate scope adjustments with the state grant agency as needed. Staff will return if additional funding is secured or if scope changes are necessary.